Windham Route 111 Roundabouts: The Study and What Comes Next

On September 28, public comment on Route 111 ran in the Town Hall meeting room on North Lowell Road until the chair closed it at 9:05 p.m. A business owner, a career truck driver, committee members, commuters and residents of side streets all took turns at the microphone. They were reacting to a drawing of the 1.6 miles of road most of Windham drives every day, from London Bridge Road and Ledge Road east to Wall Street.

The plan carries an estimated cost of about $50 million and no construction date. The project has never been in the state's Ten-Year Plan. The state has also told regional planners not to take new projects in the current update cycle, and Windham's last corridor study, finished in 2011, never got built because the town couldn't agree on it. Over the next few years, the open question is whether Windham can agree on one option.

What Alternative 5 Puts on the Map

The New Hampshire Department of Transportation's project page still lists the Route 111 Corridor Study as "Planning." Tom Errico of the consulting firm TY Lin presented the final recommendation to the Select Board. He weighed five options: Do Nothing, Transportation System Management, Five Lanes, Four Lanes and a Four Lane Hybrid. The team recommended the hybrid, Alternative 5. According to the Select Board minutes, it includes:

  • Roundabouts at all major intersections except Post Office/Village Green, which would keep its traffic signal
  • A 10-foot shared-use path on the south side of Route 111
  • A 5-foot sidewalk on the north side
  • A total of no more than five roundabouts
  • An estimated cost of about $50 million

The intersections under study are the ones Windham drivers already know by heart. NHDOT's June 24, 2025 public meeting presentation includes Alternative 5 sheets for London Bridge Road/Ledge Road, Lowell Road/Hardwood Road, North Lowell Road/Fellows Road, Church Road, Post Office/Village Green and Wall Street/Enterprise Drive. Errico told the board that North Lowell Road would likely need more capacity and that the Church Road area "still needs to be worked out." So the final design at each corner isn't settled.

The study's own numbers make the case for doing something. Errico reported about 600 crashes over the 10 years of data the team collected. He projected that traffic on the corridor will grow about 30 to 40 percent between now and 2048. He also said that speeds are high, especially west of the town center, and that there is very little infrastructure for walking or biking. The road right-of-way is 100 feet wide. Errico said some stone walls and wetlands would be affected and some widening could happen.

Where the Room Disagreed

The plan's biggest obstacle is the disagreement in that room, which made the evening worth sitting through.

Al Gabord, who owns the Commons plaza, said he was speaking for the 28 businesses there. He noted that the drawing showed no roundabout or signal near the plaza, and he asked whether the 30 to 40 tractor trailers that serve it, some 82 feet long, could get through a roundabout. Errico said large trucks will be able to. Bob Windmill of International Road, a CDL Class A driver for 50 years, said otherwise. In his view, tires get damaged when wheels ride up on a roundabout's apron, and fire apparatus could be slowed down. Al Letizio, who sat on the advisory committee, said he had talked with truck drivers about roundabouts and none of them raised concerns.

Left turns came up again and again. Ralph Glynn said his biggest worry was losing the left-hand turn, and he said he thinks 30 percent of the business will be lost. Mark Cafua asked for full left-in, left-out access to protect local businesses. Frank Corey of Red Fox Road spoke for residents west of London Bridge Road. He said that removing traffic lights would also remove the gaps in traffic that side-street drivers count on to pull out.

The Select Board was split the same way. Roger Hohenberger worried that roundabouts would remove the "metering effect" of traffic lights. He also raised concerns about emergency vehicles getting through without Opticom signal systems. Michelle Stith supported Alternative 5 and said its split median leaves room for public safety access. Chair Ross McLeod strongly supported roundabouts. He cited research from other towns showing benefits for local businesses and fewer severe crashes, but said he had a slight concern that the one remaining signal could back traffic up into the roundabouts next to it. The board took no vote on an alternative. It agreed to schedule a workshop with the Southern New Hampshire Planning Commission to talk through phasing and funding.

Windham Has Been Here Before

The 2011 study is why that split matters. NHDOT's project FAQ says a Route 111 corridor study was completed in July 2011. It produced recommendations and a final report, but "consensus within the community on these recommendations was not achieved and therefore no projects moved forward." The FAQ also says plainly, "Community consensus is key to moving a project forward."

The same FAQ describes the current study as planning only. Its product is a booklet of data and concepts, and "the Study does not produce any construction work." At the September meeting, NHDOT's Wendy Johnson told the room the next move belongs to Windham. According to the minutes, the town has to say what it supports before the proposal can go to the regional planning commission, and even if the town decided that night, it would be another 10 years.

The State's Calendar Is Closed for Now

A project like this one reaches the Ten-Year Plan through the regional commission, the Southern New Hampshire Planning Commission. An April 2026 SNHPC presentation lays out the normal cycle:

  1. In the spring of an even-numbered year, SNHPC updates its scoring criteria and asks municipalities to submit candidate projects.
  2. Candidate projects get an engineering review and a first evaluation.
  3. SNHPC sends NHDOT a shortlist, NHDOT responds, and SNHPC submits final priorities that fit the available funding.
  4. In the summer or fall of an odd-numbered year, NHDOT releases a draft Ten-Year Plan and public hearings begin.

The same presentation explains why the next update, covering FY 2029 to 2038, won't follow that cycle. In the last update, the state cut projects statewide, including several in the SNHPC region. The causes are still in place, among them flat revenue, rising construction costs and I-93 debt service. NHDOT has told regional commissions not to ask for new projects this time. SNHPC will instead review the projects already in the FY 2027 to 2036 plan and confirm priorities in case new money arrives, for example through federal reauthorization.

Route 111 isn't one of those existing projects. SNHPC's David Tilton told the board the corridor "was never in the 10-year plan," though there is a placeholder for whatever the study recommends. Town Administrator Michael Branley noted that the state updates its list every two years. Tilton added that every project is, in effect, competing against the others. Kevin Rochford of Timberlane Road asked who Windham is competing with. Tilton said 14 other communities belong to the commission, and he said the regional allocation is about $10.6 million.

That $10.6 million regional figure and a $50 million corridor estimate explain why Tilton and Branley both mentioned grants and other funding sources at the same meeting.

The Smaller Asks Run on a Shorter Clock

Several speakers on September 28 asked for things that don't depend on a $50 million rebuild. None of them is approved or scheduled. They're simply the requests that could move sooner.

Request Who raised it
Synchronize the existing traffic lights now Wayne Morris
A safety audit and medians along the full corridor Wayne Morris
A signal at Meetinghouse Road to meter traffic Dave Martsolf, Nashua Road
Safe bike crossings of Route 111 Amitot Sukhija, Ashton Park Road
Bike and sidewalk access from Route 111 to the Rail Trail Ms. Savita

On the crossing question, Errico pointed to the south-side shared path and mentioned a crosswalk with a rectangular rapid flashing beacon. Letizio described a sidewalk network that already reaches from Route 28 in Salem down to Exit 3 and along Enterprise Drive. He said he hopes the London Bridge end of Route 111 will one day connect to it. Bob Lynn asked the board not to pick Do Nothing, and Morris asked that the plan "not die on the vine."

What to Watch After November 5

As of the September 28 minutes, the Select Board workshop with SNHPC on phasing and funding had no date. McLeod suggested that the next step could be a process meeting with the board, and the board asked Tilton to come back and explain the process at a future meeting. When that workshop appears on a Select Board agenda, Windham will start answering the question that stopped the 2011 study: whether the town backs one option clearly enough to send it to the regional commission. The board's agendas and minutes are posted in the town's Agenda Center, and NHDOT keeps the study files on its Windham 40663 project page.

Route 111 is the road everyone in Windham uses to get anywhere, and how it's planned matters whether you're staying put or getting ready to list. If you want to talk about how corridor plans like this one come up with buyers on the Route 111 side streets, call or email Chris Pascoe. You'll get a straight answer from someone who drives that road too.